Certified Lean Six Sigma Supply Chain Professional (CLS) Practice Test 1

0/20 answered

Question 1 of 20

Quality control measures reveal that despite the recent implementation of a Kanban system, work-in-process (WIP) levels are consistently exceeding established limits and production bottlenecks are occurring because operators are continuing to produce items even when Kanban cards are not present at the workstation. As the Supply Chain Manager, what is the most effective action to restore the integrity of the visual production control system?