Certified Professional Contract Manager (CPCM) Practice Test 1
0/20 answered
Question 1 of 20
Stakeholder feedback indicates that several key internal departments feel overwhelmed by technical jargon and are concerned about the potential impact of a new logistics outsourcing contract on their daily operations. When performing a risk assessment of the communication plan, which approach should the procurement professional take to mitigate the risk of stakeholder resistance?